Modernisation and Re-Start of the Beacon Mill, Monarque Mining Corporation - ASDR Canada

Modernisation and Re-Start of the Beacon Mill, Monarque Mining Corporation

ASDR
shutdown_services_industriels_convoyeurs_maintenance

Mandate and Objectives

The Beacon mill is located less than 10 km from the Beaufor mine, owned by Monarch Mining Corporation. ASDR participated in the modernization and re-start of the ore processing plant. The mandate was to replace the electrical distribution network and implement a new ABB PLC control system and network. ASDR also rehabilitated production equipment and added new equipment and associated structures.

Challenges and Issues

  • Short lead times for re-commissioning versus time required for engineering 
  • Procurement delays and lack of specialized labor due to COVID
  • Lack of technical information on existing equipment

Solutions and Achievements

  • Engineering and procurement (electrical and I&C)
  • Mechanical and structural engineering for modifications and the addition of certain equipment 
  • Procurement assistance (dust suppression and ventilation)
  • Complete modernization of electrical and automation system including programming and commissioning
  • Addition of waste sieve to grinder and dust collector to crusher
  • Structural modifications and reinforcement 
  • Modified mill layout
  • Client Monarque Mining Corporation
  • Services provided • Electrical engineering
    • Replacement of the electrical
    distribution network
    • Implementation of a new
    control system and network
  • Place Val-d’Or, Quebec