Background
Agnico-Eagle was seeking an experienced partner to manage the cost and construction of surface and underground infrastructure. The entire project had to be completed according to a pre-determined schedule.

Work performed
ASDR deployed a team of highly skilled professionals to ensure the project’s success. ASDR’s professionals were present throughout the entire project over a period of more than three years.
Performance and results
- Avoided cost overruns and met timelines in a context of optimal health and safety;
- Developed a relationship of trust with the client;
- Ensured the long-term performance of work at Agnico-Eagle’s mine and other mining operations; and
- Overall assessment: $800 M
Need more info?
Stephen Authier
President
[email protected]
Tél. : (819) 757-3039 post 10302